33rd Avenue at US Highway 30 -The contractor's dirt crew started work on 7/1-Intersection will be closed beginning on Monday, 7/7 and will remain closed for 2-3 weeks-Paving crew to move in the week of 7/14- The contractor is hoping to be paving the right-turn lane the week of 7/14-Shoulder rock and traffic paint will be installed after the concrete paving has cured
32nd Avenue at US Highway 30-Excavation crew to mobilize in approximately 2 weeks-The contractor will conduct work within the lane closure and the intersection remains open;-Once 33rd Ave is open to traffic. this intersection will close and remain closed for 4-5 weeks
Ellis Road and Benton-Linn (north of 71st):-71st St/Benton-Linn Rd intersection north to Ellis Rd and east to the Cedar Rapids city limits-Intersection work includes HMA (hot-mix asphalt) in all directions. Sealcoat to be placed over the thin HMA lift.